Question: 1 / 240

Which of the following is considered a soft cost associated with a project?

Labor

Materials

Utilities

Soft costs refer to expenses that are not directly tied to the physical construction of a project but are essential for the project's overall success. These costs typically include items such as project management, financing, legal fees, permits, and utilities associated with the project.

Utilities, as indicated in the correct answer, fit into this category because they are ongoing operational costs necessary for a project but are not part of the direct construction expenses. These costs are often incurred before and after the actual construction takes place, affecting the overall project budget and financial planning.

In contrast, labor, materials, and heavy equipment rental are considered hard costs. Hard costs are directly associated with the construction process itself, including the physical aspects of building a project. Labor covers workers' wages, materials encompass the raw inputs needed for construction, and heavy equipment rental is tied to the machinery used during construction. All these are crucial for the physical execution of the project and thus fall under hard costs rather than soft costs.

Get further explanation with Examzify DeepDiveBeta

Heavy equipment rental

Next